Standard Operating Procedure (SOP) for Line Clearance (LC) of the manufacturing area and equipment at the different stages of drug product manufacturing and packing in a pharmaceutical manufacturing plant.
Procedure for Line Clearance of Area and Equipment
1.0 PURPOSE :
-
- The purpose of this SOP (Standard Operating Procedure) is to describe the procedure for clearance of line, area and equipment in production and warehouse department.
2.0 SCOPE:
-
- This procedure is applicable to –
-
-
- Batch to the batch changeover of area and equipment.
-
-
-
- Product to product changeover of area and equipment.
-
-
- Startup clearance for starting of new batch/product or continuation of the previous batch for the next day, at the pharmaceutical manufacturing plant.
3.0 REFERENCES:
-
- In House
-
- SOP for General Cleaning Procedure for Production Area.
4.0 RESPONSIBILITY:
-
-
Production operator and Warehouse Personnel shall be responsible for
-
-
- Maintaining the area(s) and equipment(s) cleanliness in their respective area, as per the relevant type of cleaning as per the defined procedure,
-
- So that no remnants of previous batch(s) / product(s), are left out in the area/equipment.
-
- Ensure the use of proper gowning, hand gloves, nose mask and secondary gowning of the personnel working in the Primary area during line clearance (LC) and operations.
-
- Production and warehouse personnel shall ensure the intactness of the connection of static charge dissipator and earthing.
-
- Production and warehouse Personnel shall be responsible for taking line clearance (LC)of area and equipment for their respective area(s).
-
- Maintain the activity in BMR/BPR/equipment Sequential log/Line Clearance Record and Line Clearance.
-
- Intimating Quality Assurance officer for line clearance (LC) in advance for respective equipment(s) and area(s).
-
-
Production and warehouse Department head shall be responsible for –
-
-
- Ensure proper implementation of the SOP.
-
-
QA department / QA personnel shall be responsible for –
-
-
- Ensure differential pressure of the respective area is within the limits and check entry of the same in the logbook.
-
- QA shall ensure that temperature and relative humidity is complying as per the established limits or product requirement and check the entry of the same in the logbook and BMR/BPR/Line clearance checklist as applicable.
-
- Visually ensure the cleanliness of the area/equipment (s) so that no remnants of previous batches/products, as per the type of cleaning are left out in the area/equipment (s).
-
-
Also, check the Qualification/Calibration and Preventive Maintenance tags for verifying the validity.
-
-
- QA, Production and Warehouse Personnel shall follow the instructions described in the Line clearance (LC) checklist of BMR/BPR/ attached checklist sheet.
-
- Ensure that calibration of the weighing balances are performed by using calibrated weight box and check the entry of the same in the logbook.
-
- Ensure the gowning of the person described as per the SOP of “Entry and Exit procedure for primary area” for the intended area.
-
- QA shall ensure the personnel working in the area shall wear the PPE (personal protective equipment) as per the SOP of “Entry and Exit procedure for primary area”-(BSPN/023) for the intended area.
-
- Follow the additional instructions if any as per BMR/BPR during the line clearance (LC).
-
- Ensure all the logbooks are filled and duly checked by warehouse / production officer / executive applicable to that particular area. QA may sign on the remark column or re-verify the entries made.
5.0 ABBREVIATIONS:
-
- AQL: Acceptable Quality Level
-
- BMR: Batch manufacturing record
-
- BOM: Bill of Material
-
- BPR: Batch Packing Record
-
- BQS : Blistering Quickly Through Servo
-
- FBD : Fluidized Bed Dryer
-
- IPQA: In-Process Quality Assurance
-
- ITW : Illinouis Tool Works
-
- M/C : Machine
-
- RLAF : Reverse Laminar Air Flow
-
-
DEFINITION:
- Area Clearance: It is defined as the clearance certification for the area, to be used for the next batch/product, performed by the concerned officer and checked by QA officer before starting a new batch/product.
-
-
- Equipment Clearance: It is defined as the clearance certification for the equipment, to be used for the next batch/product, performed by the concerned officer and checked by QA officer before starting a new batch/product.
-
- Start-up Clearance: It is the checks performed by the concerned officer and checked by the QA officer before starting a new batch/product.
6.0 PROCEDURE FOR LINE CLEARANCE (AREA & EQUIPMENT):
-
- General Instruction for Line Clearance:
-
- Cleaning of production area shall be done as per SOP of “General Cleaning Procedure for Production area”.
-
- Proper status labeling of the area shall be ensured as per SOP of “Status Labelling”.
-
- Line clearance (LC) shall be given for various areas as per the procedure mentioned below for the particular area.
-
- Line clearance to be performed only in the dismantled condition of equipment’s part.
-
- During product change over, Production and QA shall ensure the cleanliness of the area, each major part of the equipment, change part, gasket, lids, hoppers, cabinets, brush, etc.
-
- If the area conditions, documents & the required cleanliness as per the type of cleaning are satisfactory then fill the ‘Line clearance checklist’ as per the relevant Annexure-2/3/4 or respective BMR/BPR and sign along with the date in the required column(s).
-
- All line clearance given is valid for 48 hours.
-
- In case the area is not used after taking the line clearance for more than 48 hours, again line clearance shall be taken as per the procedure defined.
-
- If any discrepancies are observed by QA during line clearance, it shall be brought to the knowledge of the concern area in-charge.
-
- The activity shall be started after necessary CAPA is implemented or the observed discrepancies are rectified.
-
- However, during line clearance, if the discrepancies are repeated, then an event shall be raised for the same as per the respective SOP for Incident / Deviation.
-
-
Line Clearance During Dispensing :
-
-
- Warehouse personnel shall intimate QA for line clearance after segregating all the approved materials to be dispensed for a batch as per MIO and BOM.
-
- QA shall verify the correctness of raw material by checking the Material name, Material grade (if applicable), Item code, A.R. Number (QC Ref. No), Mother Label on containers/ bags.
-
- QA shall ensure that there is no physical damage to the container/s and is /are during the time of dispensing.
-
- In case loose container/s is/are used for dispensing; the same shall bear a status label as per SOP of “Dispensing of Raw Material”.
-
- In case intact container/s is/are used for dispensing; the same shall also bear a status label as per SOP of “Dispensing of Raw Material”.
-
- QA shall check the area around the dispensing room and ensure the cleanliness of the scoop, RLAF, Vacuum cleaner, spatula, liquid dispenser, etc. during line clearance.
-
- Warehouse personnel shall perform the dispensing activity after getting line clearance from QA.
-
- Warehouse personnel shall follow the sequence to dispense the raw material as per the SOP of “Dispensing of Raw Material”.
-
- Some of the critical parts (but not limited to) to be checked are shown below :
-
-
Line Clearance During Granulation :
- Production officer /executive shall intimate to QA officer for line clearance after ensuring the proper cleaning of area & equipment(s).
-
-
- QA shall check the area and equipment cleanliness.
-
- All the equipment shall be labeled as “CLEANED “at the time of line clearance.
-
- QA shall ensure the completeness of BMR up to the previous stage.
-
- QA shall verify the weight of API(s) after the line clearance.
-
- After satisfactory checking, QA shall provide the line clearance and sign the BMR.
-
- The production officer/executive shall start the manufacturing activity after getting line clearance from QA.
-
- Checkpoints: Some Photos of Difficult to Clean Parts (but not limited to) in Granulation are shown below :
-
- Sifting/milling & dry milling stage:
-
-
- Comminuting Mill: Feeding Augar & Hopper, Blade & Screen
-
-
-
- Paste Preparation Cattle:
- Paste Cattle Stirrer:
-
-
- Mixing & Granulation Stage:
-
-
- RMG: Impeller,
-
-
-
- The inner wall of the lid,
-
-
-
- Feeding chute,
-
-
-
- CO- Mill,
-
-
-
- RMG Chopper,
-
-
-
- Discharge Chute,
-
-
-
- RMG Discharge Chute of CO-MILL,
-
-
-
- Scrapper.
-
-
- Drying Stage :
-
-
- FBD Trolley & Sampling Port
-
-
-
- FBD – Dutch mesh of Trolley
-
-
-
- Bottom of Plenum
-
-
-
- View glass in Retarding chamber
-
-
-
- Outside view
-
-
-
- Tray Dryer: Outside view, Inner View, Tray
-
-
- Roll Compactor :
-
-
- Compactor Screen
-
-
-
- Feeding Augar
-
-
-
- Compaction Roller
-
Line Clearance During Blending :
-
-
- Production officer /executive shall intimate to QA officer for line clearance after ensuring the proper cleaning of area & equipment(s).
-
- QA shall verify the cleanliness of the bunker to be used for blending purposes.
-
- The bunker shall be labeled as “CLEANED” at the time of LC.
-
- QA shall ensure the completeness of BMR up to the previous stage.
-
- After satisfactory reviewing of documents, logbooks, and area, QA shall provide the LC and sign the BMR.
-
- Production and QA shall verify the unique container no., cable tie no., gross weight, tare weight and net weight with respect to BMR.
-
- Production officer/executive shall start blending activity after getting line clearance from QA.
-
- Ensure that the weights of the containers/bins are recorded accurately in the respective BMR.
-
- CheckPoints: Mentioned the difficult to clean parts (but not limited to) of Bunker :
-
-
- Bunker: Lid Inner Surface
-
-
-
- Bunker: Inner walls
-
-
-
- MTS: Material Transfer System
-
-
-
- MTS – Feeder:
-
-
-
Line clearance during compression :
-
-
- Production officer /executive shall intimate to QA officer for line clearance after ensuring the proper cleaning of area & equipment(s).
-
- QA shall verify the cleanliness of the area and equipment to be used for compression.
-
- Ensure the completeness of BMR up to the previous stage.
-
- QA shall ensure that the correct containers are being issued from the quarantine area for compression.
-
- Production and QA shall verify the unique container no., cable tie no., gross weight, tare weight and net weight of containers with respect to BMR.
-
- QA shall follow the additional instructions if any as per the BMR to provide the LC.
-
- After ensuring all the checkpoints, QA shall sign the BMR for LC.
-
- After getting LC, the production officer/ executive shall bring the containers to the compression area.
-
- The production officer/executive shall ensure the correct set of punch is being issued for the batch and its issuance details and verified by QA.
-
- The production officer/executive shall start compression activity after getting LC from QA.
-
- CheckPoints: Mentioned below the difficult to clean parts (but not limited to) of Compression machine:
-
-
- Compression M/C – Turret
-
-
-
- Hopper
-
-
-
- Feed Frame
-
-
-
- Discharge chute
-
-
-
- Force Feeder
-
-
-
- Turret with Punch
-
-
-
- Inside M/C guard
-
-
-
- De-Duster
-
-
-
- Vibrator
-
-
-
- Metal Detector
-
-
-
- Scoop
-
-
-
- SS Perforated Bowl
-
Line Clearance During Encapsulation :
-
-
- Production officer /executive shall intimate to QA officer for line clearance after ensuring the proper cleaning of area & equipment(s).
-
- QA shall verify the cleanliness of the area and equipment to be used for the activity.
-
- Ensure the completeness of BMR up to the previous stage.
-
- QA shall follow the additional instructions, if any, as per BMR to provide the line clearance.
-
- QA shall sign the BMR for LC.
-
- The technical staff of the Production department shall ensure that the correct set of change parts are being issued for the batch by verifying the respective change parts issuance record.
-
- The production officer/executive shall ensure that the correct containers/bins are being issued from the quarantine area for encapsulation.
-
- The production officer/executive shall start encapsulation activity after getting LC from QA.
-
- CheckPoints: Mentioned below the difficult to clean parts (but not limited to) of Capsule machine:
-
-
- Hopper
-
-
-
- Empty Capsule Sorter Elevator
-
-
-
- De Dusting & Polishing Unit
-
-
-
- De-Dusting & Polishing Brush
-
-
-
- Capsule: Mini Capsule shorter
-
-
-
- Empty Capsule Shorter
- Mini Capsule shorter
-
-
-
- Air Displacement Unit
-
-
-
- Capsule feeding magazine
-
-
-
Line Clearance During Coating :
-
-
- Production officer /executive shall intimate to QA officer for LC after ensuring the proper cleaning of area & equipment(s).
-
- Production officer/executive shall intimate QA person for LC.
-
- QA shall verify the cleanliness of the area and equipment to be used for coating.
-
- Ensure the completeness of BMR up to the previous stage.
-
- QA shall follow the additional instructions, if any, as per BMR to provide the LC.
-
- Sign the BMR for LC.
-
- QA shall check that the core tablets and containers are correct with respect to the batch number and lot number before issuance from the quarantine area for coating.
-
- The production officer/executive shall start a coating activity after getting LC from QA.
-
- CheckPoints: Difficult to clean parts (but not limited to) are depicted below:
-
-
- Coating Machine
-
-
-
- Perforated Coating Pan
-
-
-
- Coating Pan Baffles
-
-
-
- Nozzle Spray Gun
-
-
-
- Suspension Tank with Stirrer
-
-
-
- Colloidal Mill
-
-
-
- Colloidal Mill inner View
-
-
-
Line Clearance During Inspection of Tablets and Capsules :
-
-
- Production officer/executive shall intimate QA person for line clearance.
-
- QA shall verify the cleanliness of the area and equipment to be used for inspection.
-
- QA shall ensure the completeness of BMR up to the previous stage.
-
- Follow the additional instructions if any as per BMR to provide the line clearance.
-
- QA shall ensure that the correct containers are being issued for inspection.
-
- QA shall sign the BMR for line clearance.
-
- The production officer/executive shall start inspection activity after getting line clearance from QA.
-
-
Line clearance during primary packing :
-
-
- Production officer /executive shall intimate to QA officer for line clearance after ensuring the proper cleaning of area & equipment(s).
-
- QA shall verify the cleanliness of the equipment and area.
-
- Ensure the completeness of BMR up to the previous stage.
-
- QA shall follow the additional instruction, if any, as per BPR to provide the line clearance.
-
- Production and QA shall ensure that all the packing materials are correct and approved by QC before the start of the operation.
-
- QA shall sign the Annexure-2 or BPR for line clearance.
-
- Production and QA shall verify that the correct batch number and product are being issued from the manufacturing quarantine area to the primary parking area.
-
- The production officer/executive shall start the packing activity after getting LC from QA in the BPR.
-
- CheckPoints: Difficult to clean parts (but not limited to) during Primary packing is depicted below:
-
-
- Blister M/C: Hopper
-
-
-
- Linear Vibrating Plate & Channel
-
-
-
- Channel & Guide Track
-
-
-
- Rotary Vibrating plate
-
-
-
- Feeding Box
-
-
-
- Blister Feeding Brush with the Guide track
-
-
-
- Defoiler Machine
-
-
-
- BQS : Cavity Forming Plate
-
-
-
- Sealing Plate
-
-
-
- Indexing Station
-
-
-
- BQS Machine
-
-
-
- Strip Machine: Feeding Channel
-
-
-
- Strip Defoiling Machine
-
-
-
- Tablets / Capsules Inspection Tray
-
-
-
- Strip Machine: Collator – 01
-
-
-
- Strip Machine: Collator-02
-
-
-
Line clearance during Secondary packing :
-
-
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (For secondary area) as per Annexure-4 or as per BPR.
-
- Production officer/executive shall intimate QA person for line clearance.
-
- QA shall verify the cleanliness of the equipment and area.
-
- Ensure the completeness of BPR up to the previous stage.
-
- QA shall follow the additional instruction if any as per BPR to provide the line clearance.
-
- QA shall verify & ensure the correct recipe of show box coding machine.
-
- Production and QA shall ensure that all the packing materials are correct and approved by QC before the start of the operation.
-
- QA shall sign the Annexure-4 or BPR for line clearance.
-
- The production officer/executive shall start the packing activity after getting line clearance from QA.
-
- CheckPoints: (but not limited to) during secondary packing is depicted below:
-
-
- Conveyor Belt
-
-
-
- Check Weigher
-
-
-
- Parle Machine: For Mono carton Packing
-
-
-
- Auto Cartonator Machine
-
-
-
- Check weigher with the lid open
-
-
-
- Shipper Sealing Machine
-
-
-
Line clearance during Offline-Secondary packing :
-
-
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (For secondary area) as per Annexure-4 or as per BPR.
-
- Production officer/executive shall intimate QA person for line clearance.
-
- QA shall verify the cleanliness of the equipment and area.
-
- Ensure the completeness of BPR up to the previous stage
-
- QA shall follow the additional instructions, if any, as per BPR to provide the line clearance.
-
- Production and QA shall ensure that all the packing materials are correct and approved by QC before the start of the operation.
-
- QA shall verify & ensure the correct recipe of show box coding machine.
-
- Sign the Annexure-4 or BPR for line clearance.
-
- QA shall verify that the correct batch number and product are being issued from the manufacturing quarantine area to the primary packaging area.
-
- The production officer/executive shall start the packing activity after getting line clearance from QA in the BPR.
-
-
Line Clearance During Off-Line Coding, Labelling :
-
-
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (for the secondary area) as per Annexure-4 or as per BPR.
-
- Production officer/executive shall intimate QA person for line clearance.
-
- QA shall verify the cleanliness of the equipment and area.
-
- Ensure the completeness of BPR up to the previous stage.
-
- QA shall follow the additional instruction, if any, as per BPR to provide the line clearance.
-
- Ensure that all the packing materials are correct and approved by QC before the start of the operation.
-
- QA shall sign the Annexure-4 or BPR for line clearance.
-
- QA shall verify that the correct batch number and product are being issued from the manufacturing quarantine area to the primary packaging area.
-
- The production officer/executive shall start the packing activity after getting line clearance from QA in the BPR.
-
-
Line Clearance during Bottle Filling (Primary Area) :
-
-
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (For bottle filling) as per Annexure-2 or as per BPR.
-
- Production officer/executive shall intimate QA person for LC.
-
- QA shall ensure the completeness of BMR up to the previous stage.
-
- Then check the cleanliness of the area and various equipment/components like unscrambling chamber, air-jet cleaning apparatus, turntable, Header 1 & Header 2, PIB (material transfer system), hose pipe, capping machine, torque machine, etc.
-
- QA shall follow the additional instruction, if any, as per BPR to provide the LC.
-
- Ensure that all the packing materials are correct and approved by QC before the start of the operation.
-
- QA shall sign the Annexure-2 or BPR for LC.
-
- Once the line clearance is taken, the setting of the machine can be done.
-
- QA shall verify that the correct batch number and product are being issued from the manufacturing quarantine area to the primary packaging area.
-
- The production officer/executive shall start the packing activity after getting line clearance from QA in the BPR.
-
-
CheckPoints: Difficult to clean parts (but not limited to) during Primary Bottle packing is depicted below:
- Bottle : Air Jet Bottle Cleaning
-
-
-
- Dry Filling M/C
-
-
-
- Dosing Hopper
-
-
-
- Hopper inner view
-
-
-
- Dosing Hopper
-
-
-
- Cap Feeder
-
-
-
- Cap Feeder inner view
-
-
-
- Re-torquer
-
-
-
- Hosepipe
-
-
-
- Bottle: Conveyor Belt
-
Line Clearance during Bottle Filling (Secondary Area) :
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (For secondary area) as per Annexure-4 or as per BPR.
-
-
- Production officer/executive shall intimate QA person for LC.
-
- QA shall verify the cleanliness of the area and various equipment/components like induction sealing machine, re-torquer, turntable, check-weigher, ITW, etc.
-
- Follow the additional instructions, if any, as per BPR to provide the LC.
-
- QA shall sign the Annexure-4 or BPR for line clearance.
-
- Production and QA shall ensure that all the packing materials to be used in the secondary area are correct and approved by QC before the start of the operation.
-
- The production officer/executive shall start the packing activity after getting line clearance from QA in the BPR.
-
-
- Bottle-11: Cap liner sensor
-
-
-
- Induction Sealing M/C
-
-
-
- Round table
-
-
-
- Bottle re-torquer
-
-
-
- Check Weigher
-
-
-
Line Clearance during Sachet Filling (Primary Area) :
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (For sachet filling) as per Annexure-2 or as per BPR.
-
-
- Production officer/executive shall intimate QA person for LC.
-
- QA shall ensure the completeness of BMR up to the previous stage.
-
- Then check the cleanliness of the area and various equipment/components like a hopper, lid, collar assembly, powder tube, etc.
-
- QA shall follow the additional instruction, if any, as per BPR to provide the LC.
-
- Ensure the correctness of all the packing materials and approved by QC before the start of the operation.
-
- QA shall sign the Annexure-2 or BPR for LC.
-
- Once the line clearance is taken, Do the setting of the machine.
-
- Production and QA shall verify that the correct batch number and product issued from the manufacturing quarantine area to the primary parking area.
-
- The production officer/executive shall start the packing activity after getting line clearance from QA.
-
-
- Sachet-01: Hopper
-
-
-
- Sachet Machine
-
-
-
- Conveyor Belt
-
Line Clearance during Sachet Filling (Secondary Area) :
- Production officer/executive must ensure that the area and equipment are ready for Line Clearance (For secondary area) as per Annexure-4 or as per BPR.
-
-
- Production officer/executive shall intimate QA person for LC.
-
- QA shall verify the cleanliness of the area and equipment.
-
- QA shall follow the additional instructions, if any, as per BPR to provide the LC.
-
- Sign the Annexure-4 or BPR for line clearance.
-
- QA shall ensure that all the packing materials to be used in secondary area are correct and approved by QC before start of the operation.
-
- The production officer/executive shall start the packing activity after getting LC from QA in the BPR.
Note: Difficult to clean equipment part “Template” shall be displayed at each room with photos of items.
-
-
Issuance and Filling Procedure of Logbook:
- User Dept. Shall request for new area and equipment usage logbook in advance and before completion of previous logbook.
-
-
- User Dept. shall fill the details in request form and handover to QA for issuance of the logbook.
-
- QA shall issue the new logbook after receiving the request form.
-
- Once a new logbook is issued, the User Dept. shall use the newly issued logbook from the same date onwards.
-
- User shall put NA in the blank pages/spaces, (if any), in the previous logbook and return the same to QA.
-
-
User Dept. shall use appropriate activity code in the activity column. Activity Code :
-
-
-
- Type A cleaning – A
-
-
-
- Type B cleaning – B
-
-
-
- Routine Cleaning – R
-
-
-
- Process – P
-
-
-
- Maintenance – M
-
-
-
- Preventive Maintenance – PM
-
-
-
- Fumigation – F
-
-
-
- Break down – BD
- Qualification – Q
-
-
-
- Continued – CNTD
-
-
- User Dept. shall put activity code ‘A’ in the activity code column of logbook if area and equipment cleaning to be done for the batch to batch.
-
- User Dept. shall put activity code ‘B’ in the activity code column of logbook if area and equipment cleaning to be done for product to product.
-
- Put activity code ‘R’ in the activity code column of logbook if area and equipment cleaning to be done for routine cleaning before starting the continued activity.
-
- User Dept. shall put activity code ‘M’ in the activity code column of logbook if area and/or equipment are under maintenance.
-
- User Dept. shall put activity code ‘PM’ in the activity code column of logbook if the equipment is under preventive maintenance.
-
- Put activity code ‘Q’ in the activity code column of logbook if area and/or equipment are under qualification.
-
- User Dept. shall put activity code ‘BD’ in the activity code column of logbook if the equipment is under break down.
-
- User Dept. shall put activity code ‘F’ in the activity code column of logbook if the area is under fumigation.
-
- Put NA if any column is not applicable for that activity in the logbook.
-
- User Dept. shall put an appropriate remark in remark column like Batch over, Batch Continue, Routine Cleaning in the logbook (Annexure 5).
-
Conditional Line Clearance:
- Provide the conditional LC at the packing stage at the activities like capsule filling, coating or compression completed up to the required stages.
-
- Take the temporary change / planned deviation procedure for the same.
-
- If any discrepancy is observed at capsule filling, coating or compression stage. Do not allow the conditional LC at the packing stage.
-
- The transferring department shall raise the temporary change / planned deviation.
-
- Transfering department shall fill the details and forward the filled deviation IPQA for verification of required information as per Annexure 3 of SOP Incidents / Deviations.
-
- After satisfactory review of deviation for conditional LC by IPQA, IPQA shall forward the deviation for final approval to Head QA/ Quality Head/Designee.
-
- During conditional LC at the packing stage, BMR shall remain with the manufacturing department.
-
-
LC shall be given at the packing stage after ensuring the approval of the planned deviation.
-
-
- Approved planned deviation shall be attached with respective BPR.
-
- One photocopy of approved planned deviation for conditional LC shall also attache with BMR.
-
- During conditional LC at the packing stage, IPQA shall ensure details like Batch number, Lot number, number of containers, and quantity transferred for packing against approved planned deviation.
-
- Record the number of shipper packed against the approved planned deviation sin BMR/BPR history sheet or the footer part of the BPR of corresponding pages to capture such type of details with a remark.
-
- After completion of all processes at the manufacturing stage, Transfer the remaining quantity/lots to packing department for the completion of the batch packing activity.
-
- Take the second-time LC at the packing stage only in the Primary area to ensure the correctness of the product and remaining transferred quantity from the manufacturing department.
-
- Document the re-line clearance shall be documented as per LC checklist (Annexure2).
-
- Inline clearance check, put NA for the column which is not relevant with respect to second-time line clearance against conditional line clearance.
e.g. Put “NA” against the checkpoints like previous product.
Note 1: Second time LC shall be ensured with respect to product and the remaining quantity of the same batch shall be packed.
-
- During Re-line clearance, QA shall verify Product Name, Batch Number, Lot Number and Number of containers for packing of the remaining quantity of the batch.
Note: If the line is to be for any other product, a complete changeover and follow the line clearance procedure.
7.0 ANNEXURES / CHECKLIST – SOP FOR LINE CLEARANCE :
Annexure 1: Area and Equipment Usage Log.
Department: | Area: |
Tabulate the following table contents to make the logbook with the above header…
-
- Date
- Equipment Name
- Equipment ID
- Product Name
- Batch No.
- Shift
- Activity Code
- Activity
- Done By
- Checked By
- Remark
Annexure 2: Line Clearance Checklist.
Previous Product: | Next Product: | ||||||
Previous Batch No | Next Batch No.: | ||||||
Area : _____Stage: Date : ___________ |
|||||||
Sr. No | Check Points | Checked By | |||||
Prod. | QA | ||||||
1 | Area Clearance : | ||||||
1.1 | Ensure that the area should be cleaned. | ||||||
1.2 | Ensure cleaning of the area underneath the equipment, (if applicable) | ||||||
1.3 | Ensure that the previous product is removed from the area. | ||||||
1.4 | Ensure that the waste bin has been cleaned and the fresh polybag has been put into the bin. | ||||||
1.5 | Ensure the floor is mopped with a sanitizing agent. | ||||||
1.6 | Ensure proper status labels on the area and absence of BOPP tape on equipment and area. | ||||||
1.7 | Ensure the cleanliness of the drain point in the area. (If applicable) | ||||||
1.8 | Ensure cleaning and proper status labeling of pallets / Containers, rejection bin and their availability with lid. | ||||||
1.9 | Ensure cleaning of riser filters/return riser, grills. | ||||||
1.10 | Ensure cleaning of walls, light fixtures, balance, and its cable, Electrical panel, SOP stand, Magnehelic gauge, Thermo hygrometer. | ||||||
1.11 | Ensure that the area is within the cleaning validity period. | ||||||
1.12 | Ensure cleaning of utility pendant/dust collector. | ||||||
1.13 | Ensure proper gowning procedure/PPE. |
2 |
Equipment’s / Accessory Clearance : |
|||
2.1 | Ensure cleaning of the equipment with the proper status label. | |||
2.2 | Ensure traces analysis results are within the limits & record are attached with the BMR (If applicable) | |||
2.3 | Ensure that the equipment is within the cleaning validity period. | |||
2.4 | Ensure the equipment qualification tag is updated. | |||
2.5 | The equipment preventive maintenance tag is updated. | |||
2.6 | Ensure cleaning of balances used in the area (If applicable). | |||
2.7 | Ensure that dismantle parts (i.e. Gasket, lids, hopper, flooding brush, etc.) of the machine, safety guards and earthing points are adequately acceptable and cleaned. | |||
2.8 | Ensure that accessories to be used are cleaned and the presence of screw, bolts, and nuts on each equipment, HEPA grills and return riser. | |||
2.9 | Ensure cleanliness of hopper and their lid. |
3 |
Environmental Conditions: |
|||
3.1 | Ensure that the temperature & relative humidity of the area are with in the limit. | |||
3.2 | Ensure that the pressure differential across the area is within limits. |
4 |
Document Review : |
|||
4.1 | Ensure that the document of the previous product/label is removed from the area. | |||
4.2 | Ensure the area & equipment log are available. | |||
4.3 | Ensure the punch issuance record is updated.(If applicable) | |||
4.4 | Ensure balance calibration / daily performance/calibration label is updated & check record for the same. (If applicable) | |||
4.5 | Ensure all relevant SOP are placed in the area. | |||
4.6 | Ensure that relevant entries are recorded in the BMR/BPR. |
5 | Material / Product Verification of Proposed Run: | ||||||
5.1 | Line clearance has been given for bulk manufactured of the proposed run | ||||||
5.2 | The correctness of material/product name & A.R. No./ batch number. | ||||||
5.3 | The product is stored as per the established hold time conditions & limits. | ||||||
Production Officer | Name: | Sign: | Date: | ||||
IPQA Officer | Name: | Sign: | Date: | ||||
Note : Put (√ ) for complies / ( X ) for not complies/ ( NA ) for not applicable in column given |
Annexure 3: Line Clearance Checklist for Dispensing.
Area : | Date : | |||||
Previous Product : | Next Product : | |||||
Batch Number : | Batch Number : | |||||
Sr. No. | Description of Activity | *Observation
Warehouse |
*Observation
QA |
|||
1 | Ensure the cleanliness of the dispensing area. | |||||
2 | Ensure the proper status label on the RLAF. | |||||
3 | Ensure the removal of all materials of previously dispensed product/ batch from the area. | |||||
4 | Ensure the removal of all the documents and containers of the previous product. | |||||
5 | Ensure the clean and calibrated weighing balance as per respective SOP. | |||||
6 | Visually check the RLAF for its Cleanliness. | |||||
7 | Ensure that environmental conditions are maintained and recorded as per BMR/BPR. | |||||
8 | Ensure that the pressure differential of area and RLAF within the limit and recorded. | |||||
9 | Ensure that the RLAF started before 20 minutes from starting the dispensing. | |||||
10 | Ensure the cleanliness of return air riser filters in the area. | |||||
11 | Ensure the equipment qualification tag updated. | |||||
12 | Ensure that the SOP of cleaning and operation of equipment in place. | |||||
13 | Visually check the waste bin for its cleanliness. | |||||
14 | Ensure that the bar code scanner presence in the area. | |||||
15 | A list of light-sensitive material, nitrogen flushing, and psychotropic material are present in the area. | |||||
16 | Ensure the proper gowning procedure followed by persons | |||||
17 | Verify the details on material issue coupons with unconfirmed MRO. | |||||
Checked By | Store
Sign/Date |
QA
Sign/Date |
||||
*Put (√ ) for complies/ ( X ) for not complies/ ( NA ) for not applicable in observation column. |
Annexure 4: Line Clearance Checklist for Secondary Packing.
Previous Product: | Next Product: | ||||||
Previous Batch No.: | Next Batch No.: | ||||||
Line No.: Date : | |||||||
Sr. No | Check Points | Checked By | |||||
Prod. | QA | ||||||
1 | Area Clearance : | ||||||
1.1 | Ensure the area cleanliness. | ||||||
1.2 | Ensure the floor is mopping with a sanitizing agent | ||||||
1.3 | Check the top and below of the conveyor and ensure the absence of remnants of the previous product. | ||||||
1.4 | Ensure the cleanliness of the waste bin and fresh polybag placed into the bin. | ||||||
1.5 | Check that the line status board for updated information. | ||||||
1.6 | Check the non-recovery of the previous batch destroyed. | ||||||
1.7 | Ensure cleaning of Pallets, Containers/Rejection bin. | ||||||
1.8 | Ensure proper gowning procedure. | ||||||
2 |
Equipment / Accessory Clearance : |
|||
2.1 | Ensure that the cleaned balances used in the area. | |||
2.2 | Ensure that the cleaned accessories used in the area. | |||
2.3 | Check that mini touch over the coding machine (Condot / HSA Jet / Concept). It should clear from the data/recipe of the previous product and remove the stereos. | |||
2.4 | Ensure that the cartridge of the carton coding machine of the previous batch. Removed and replaced with the new cartridge. |
3 | Environmental Conditions: | |||
3.1 | Ensure that the pressure differential across the area is within limits |
4 | Document Review : | |||
4.1 | Ensure that the area & equipment log is available and filled properly. | |||
4.2 | Ensure that the balance calibration / daily performance/calibration label is updated & check record for the same. (If applicable) | |||
4.3 | Check that the reconciliation of the previously completed batch. | |||
4.4 | Ensure that all relevant SOP placed in the area. | |||
4.5 | Ensure those relevant entries recorded in the BPR. |
5 |
Material / Product Verification of Proposed Run: |
||||||
5.1 | The correctness of material/product name & A.R. No./ batch number. | ||||||
Production
Officer |
Name: | Sign: | Date: | ||||
IPQA Officer | Name: | Sign: | Date: | ||||
Note : Put (√ ) for complies / ( X ) for not complies/ ( NA ) for not applicable in column given |