Operation Procedure for HOIST

Standard Operating Procedure (SOP) for HOIST, containing Operation of L.T ElevatorOperation of Hyundai Elevator, Safety Precautions, etc.

SOP for HOIST

1.0       PURPOSE:

    • The purpose of this SOP is to define the procedure for the operation of the hoist.

2.0      SCOPE:

    • This procedure is applicable to the operating procedure of Hoists at the pharmaceutical manufacturing plant.

3.0      REFERENCES:
HOIST-Equipment

    • In-House

4.0     RESPONSIBILITY:

    • All users shall be responsible for operating the Hoist as per the Standard Operating Procedure.
    • Engineering Supervisor shall be responsible for maintaining the Hoist and ensure its proper operation.
    • Maintenance Head shall be responsible for checking and ensuring the safe operation of Hoist.
    • Quality Head and Plant Head or Designee shall be responsible for reviewing and approving the SOP.

5.0     ABBREVIATIONS:

    • Dept.          : Department
    • NA             : Not Applicable
    • QA             : Quality Assurance
    •  SOP            : Standard Operating Procedure

6.0     PROCEDURE OPERATION OF HOIST:

    • For Operation of L.T Elevator

    • Press the call switch to call the hoist on the desired floor.
    • Open the Sliding Doors of the cage and Place desired material inside the cage to be carried.
    • Press the floor level number to which you want to carry the material.
    • Close the Sliding Doors of the cage.
    • The cage will move automatically to the desired floor and will stop.
    • Open the sliding door and take out the material and close the door.
    • Do not load more than 2000 Kg (Kilogram) in the hoist.
    • Both Breakdown and Preventive Maintenance of Lift is to be done by the External Agency (representatives of L.T. Elevator) and Under Maintenance Label should be fixed on all the floors before starting the maintenance activity.
    • For Operation of Hyundai Elevator (HOIST) :

    • Press the call switch to call the hoist on the desired floor.
    • After the lift arrives at the desired floor, the door will open up automatically, place the desired material inside the cage.
    • Press the floor number you want to carry the material to.
    • The lift door will automatically close and take you to the desired floor and the door will open up automatically.
    • Take out the material from the lift, the door will close automatically.
    • Do not Load More than 1630 Kg (Kilogram) (or as per instruction of individual manufacturer) in the Lift.
    • Perform the Breakdown and Preventive Maintenance of Lift by the External Agency (representatives of Hyundai Elevator) and.
    • Put the under Maintenance Label in front of the lift on all the floors before starting the maintenance activity.
    • Use the hoist for both human and material movement.

Also visit : SOP and Formats for ETP / STP

    • Safety Precautions during HOIST operation:

    • Do not hit the door or any part of the Lift with the trolley/ pallet.
    • Do not panic in case of a power cut, the lift will take you to the desired floor automatically ( applicable for the individual manufacturer of  Elevator)
    • In the case of Fire or Emergency, switch ON the fire Switch located at the lower ground floor. ( applicable for the individual manufacturer of  Elevator)
    • In case you are stuck inside the lift Press Alarm Switch, it will trigger a telephonic call to respective / defined location and Lift machine room. (applicable for the individual manufacturer of  Elevator).
    • Do not Horseplay.
    • Clean the elevator by Hand moping.
    • Do not use Floor cleaning machine for cleaning the lift.

7.0      DISTRIBUTION:

    • Maintenance
    • Production
    • Quality Assurance
    • Quality Control
    • Warehouse

8.0     ANNEXURES: NA

 

pharmabeginers

Janki Singh is experienced in Pharmaceuticals, author and founder of Pharma Beginners, an ultimate pharmaceutical blogging platform. Email: [email protected]